I'm in tile mode at the moment. The tiler has been laying Ditramat on all the floors (Caber deck upstairs and screed downstairs) mainly to prevent cracking. The screed would probably have been OK without had it had more time to dry out, apparently. Ours got about 4/5 weeks, rather less than the commonly recommended one day per mm. which would have been about 3 months. Some small cracks have indeed appeared in the untiled areas of screed since then.
If you have a (slightly) unstable floor you could try this if you re-tile.